Manufacturing · Honduras
Contracted availability in milling
A five-year contract on milling utilities, with availability as the only payment metric.
99,4 %
Availability
-22 %
Maintenance cost
Cementos Talara2024
Capabilities
01Engineering and designStudies, FEED and detailed engineering02InfrastructureConstruction, installation and commissioning03Operations and maintenanceContracted asset availability04Digital transformationTelemetry, data and operating systems05Strategic consultingCapital and capacity decisions06Systems and equipmentIn-house manufacturing and specified equipment
Transforming critical operations at regional scale
A logistics operator running six terminals across three countries was moving freight on systems that did not talk to each other. We redesigned the operation of the entire corridor and instrumented it point by point.
See moreCatalogue
01AX-360 SeriesProcess pumping02TC-200 PanelControl and automation03SK-500 SkidModular assembliesAX-360 Series
Skid-mounted single-stage centrifugal pump, sized for continuous duty at altitudes and temperatures outside the standard catalogue range.
See moreAnalysis and reports
Papers from the technical team on capacity, continuity and measurement.
See moreWork
A selection of contracts delivered between 2022 and 2025. The figures are illustrative and belong to a fictional company; the structure is the one a real project file would use.
Logistics · Honduras · Guatemala · El Salvador
A logistics operator running six terminals across three countries was moving freight on systems that did not talk to each other. We redesigned the operation of the entire corridor and instrumented it point by point.
-32 %
Uptime
+46 %
Capacity
99,9 %
Availability
3
Countries
Transandina Logística2023 – 2025
Infrastructure · Colombia
Rehabilitation and sectorisation of a trunk main running at 46 % losses, carried out in sections so that supply was maintained across the twenty-six months of works.
-31 %
Physical loss
42 km
Conveyance
18
Districts metered
0
Days without supply
Grupo Meridian2022 – 2024
Energy · Honduras
Two new bays and a full protection system replacement on a live substation, with twelve hours of total outage split across two night windows.
12 h
Total outage
2
New bays
+65 MVA
Capacity
0
Protection events
Norvik Energía2024 – 2025
Manufacturing · Honduras
A five-year contract on milling utilities, with availability as the only payment metric.
99,4 %
Availability
-22 %
Maintenance cost
Cementos Talara2024
Corporate sector · Honduras · El Salvador
A redesign of the critical power chain in two halls, with transfer tested under real load and no window of unavailability.
1,32
PUE achieved
+40 %
Usable capacity
Banco Peninsular2023
Manufacturing · Mexico
Nine pumping sets replaced by a single design, with the spares inventory reduced to one family.
-28 %
Capital tied up in spares
9
Assemblies
Vega Minerals2022 – 2023
Our team can help you identify the right solution for your organisation — including when the conclusion is that you do not need a project at all.